Bangladesh’s Rooppur Nuclear Power Plant has started its second experimental electricity supply to the national grid as part of ongoing testing ahead of regular commercial operations.

The trial supply began at 10:20am on Monday (November 23), according to project officials.

Dr Mohammad Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, said the facility would supply approximately 300–350 megawatts of electricity to the national grid for 10 to 24 hours during this phase.

He said the trial would involve technical tests of the plant’s power generation system and its coordinated operation with the national grid.

The tests are intended to assess the technical performance of the power plant and ensure proper synchronisation with the country's electricity transmission system.

Earlier, the plant began its first experimental electricity supply to the national grid on November 17 at 3:16pm, delivering approximately 350 megawatts.

Monday's operation marks the second phase of the trial grid connection process as Bangladesh moves forward with testing its first nuclear power plant.